I informed myself about connecting to the Joomla! database and wrote an article here. In the meeting I checked the team's states again and published this blog.

Afterwards I collected all the milestone lists to create a complete PSP. Philipp's project team had problems with the SVN, as the repository didn't list their uploaded documents. I got them now and I'm struggling to tell MS Project that milestones aren't just planned but also achieved. Some in time, some earlier than the planned date and some later.

I've also talked to the project controllers, especially Denise and Martin, to make sure the project managers and myself get the infos we need in a status report next time. (11.12.2007)